Many Scrum books and articles say that a failed sprint (when the team fails to complete some features from the Sprint Backlog) is not something that bad, it happens from time to time, and it can actually be useful if the team learns from their mistakes and improves something in the following sprints. And the team should not be punished for not completing the work they committed to.

This looks great from the developer's point of view, however, let's say we have a software company "Scrum-Addicts LLC" developing something for serious clients ("Money-Bags Corporation"):

  1. Scrum-Addicts managers suggest making a piece of software for Money-Bags
  2. They agree on a list of features, and Money-Bags asks to provide a shipping date
  3. Scrum-Addicts managers consult their scrum team, and the team says it will take 3 week-long sprints to complete all of the features
  4. Scrum-Addicts manager adds 1 week to be safe, promises to ship the software in 1 month and signs a contract with Money-Bags
  5. After 4 sprints (shipping deadline) Scrum team can only deliver 80% of features (because of inexperience with the new system, the need to fix critical bugs in previous features in production environment, etc...)
  6. As Scrum suggests, at this point, the product is potentially shippable, but Money-Bags needs 100% of features, as mentioned in the contract. So they break the contract and pay nothing.
  7. Scrum-Addicts is on the brink of bankruptcy because they got no money from Money-Bags, and the investors were disappointed with the results and are unwilling to help the company any more.

Obviously, no software company wants to be in Scrum-Addicts' shoes. What I fail to understand about Agile and Scrum is how they suggest teams should deal with planning and deadlines to avoid the situation described above. So, to summarize, I have 2 questions:

Who is to Blame?

  1. Managers, because it's their job to do the proper planning
  2. The team, because they committed to doing more work than they could
  3. Someone else

What Is to Be Done?

  1. The managers should move the deadline 2x (or 3x) times later than the original team's estimate.
  2. Team members should be encouraged to do all the work they committed to no matter what (by issuing penalties for failed sprints)
  3. The team should drop Scrum because it doesn't fit the company deadline policy
  4. We should all drop software development and join a monastery
  5. ???
18
  • 32
    You point 3 under "To be done" assumes not using Scrum would have changed anything in having only 80% of the features ready in one month. That is ridiculous.
    – Doc Brown
    Feb 25, 2016 at 9:26
  • 7
    @DocBrown, I can't agree it is ridiculous. Dropping some Scrum activities like retrospective and demonstration meetings could speed up the development. And in case of a rock-solid contract this could help achieve the ultimate goal: deliver a fixed amount of features at the end of the deadline. Feb 25, 2016 at 10:12
  • 26
    @AndreBorges Your suggestion to dropping retrospectives and demonstrations is same as suggesting in removing brakes from a car. Sure, brakes only slow you down. But that is what allows you to go really fast.
    – Euphoric
    Feb 25, 2016 at 10:18
  • 13
    the same problem remains under any system - note that you can pretty much replace scrum with an equivalent waterfall one and the company still goes bust
    – jk.
    Feb 25, 2016 at 12:04
  • 6
    Perhaps if those Scrum-Addicts managers had paid more attention during those pesky "retrospective" meetings, they would have had the chance to hit the brake at week 1 or 2, instead of watching the project steer towards the cliff, and hit the gas pedal.
    – Dorus
    Feb 25, 2016 at 15:14

10 Answers 10

133

I see several fundamental management issues in your example:

  • if a Scrum-Addicts manager signs a "hard-deadline" contract, but adds only a safety margin of 33% in a situation where "a new system is involved", that is pretty reckless.

  • the availability of delivering at least x% of the features after one month could have been used to negotiate a contract where the customers pays the money at least partially when he gets only 80% of the features at the deadline. An all-or-nothing contract is something neither the software vendor nor the customer will benefit from - this means not just 0 money for the vendor, but also 0 features for the customer. And an all-or-nothing development methodology like "Waterfall" will only let you write such contracts, an agile approach offers additional possibilities.

  • looking at the results of the first one or two sprints should have made obvious to the manager that the team cannot meet the deadline. So he should have taken earlier actions, and re-prioritize the remaining tasks and features, or try to re-negotiate with the customer earlier. For example, the manager could have tried to downsize the scope of some of the remaining features, so the team could have delivered all features mentioned in the contract, but each of them in a reduced scope.

If a task turns out to take longer than you thought, no development methodology will save you from that. But an agile approach like Scrum gives management more opportunities to control what happens in that situation. If they don't make use of those opportunities, it is clearly their fault, not the team's, not the fault of "Scrum", and not the customer's fault because "he does not accept agility".

14
  • 48
    +1 for "An all-or-nothing contract is something neither the software vendor nor the customer will benefit from". It is the key thing about agile contracting. Feb 25, 2016 at 10:37
  • 5
    And it's certainly the case that 80% is no good for some kinds of project (ultimately it's possible, although unlikely, that agile is too limiting to make provision for those projects). So for example it's no use having 80% of the features for your satellite when you launch it, which is why you don't mess about with the contingency on those projects. If you fail to deliver then your client's mission will fail (or be delayed), there's nothing you can do in the contract to change that. Feb 25, 2016 at 11:42
  • 6
    @SteveJessop: I am pretty sure even when you build such a complex thing like software for a satellite, there are different priorities for different features, and there will be lots of features where the scope can vary to a certain degree. The deadline may be fixed for such a situation, of course, because when you don't get the rocket into space until december next year, you might get no second chance.
    – Doc Brown
    Feb 25, 2016 at 11:56
  • 6
    But for this specific example... ofcourse no one would have sent new horizons out if they failed to finish the cameras hardwaredriver. But even for projects on that scale I would bet one are not going into space with every feature that they were imagine of.
    – Zaibis
    Feb 25, 2016 at 12:46
  • 6
    perhaps paying per milestone or functionality could also be an option.
    – Bram
    Feb 25, 2016 at 13:10
67

One of the value statements of the "Manifesto for Agile Software Development" is :

Customer collaboration over contract negotiation

The fact that Scrum-Addicts LLC negotiated a contract instead of establishing a collaboration with a customer makes me question their agility.

One thing is clear : Agility needs to be accepted by EVERYONE. Agility is not only for developers. Managers and customers also need to accept the values of Agile Manifesto. If customers don't accept agility and still require rigid contracts and minimal collaboration, then either don't use agile or find better customers.

It is customer's fault they are locked in their contract bubble with deadline-driven development.

30
  • 9
    @RubberDuck There has yet to be a software project management methodology that allows features to be decided up front, deadline set and was not terribly expensive. Scope, Time, Money; Pick two.
    – Euphoric
    Feb 25, 2016 at 9:05
  • 8
    @RubberDuck: The project is already not-agile, because the requirements are set in stone. And the estimate is only three weeks. There is nothing magically bad about waterfall that makes it always late, it just can't deal with vague requirements and change. Yeah, I would use "waterfall" in this case, or more accurately "let's decide what needs to be done and do it". Feb 25, 2016 at 9:25
  • 3
    @RemcoGerlich ironically, "let's decide what needs to be done and do it" is remarkably agile itself :-)
    – gbjbaanb
    Feb 25, 2016 at 9:31
  • 2
    @RemcoGerlich ah, I think you misunderstand my point: in that agile is not really about the dev methods, but the ability to get on with the work, using whatever means you like. Its about progress not procedures after all. (eg a team that only does Scrum is not agile, a team that only does waterfall-style but modifies it to suit circumstances is)
    – gbjbaanb
    Feb 25, 2016 at 9:42
  • 2
    I agree with Doc Brown here. You can absolutely have a "time limit" without saying exactly "for what". It's perfectly reasonable to say, for instance, "Our deadline is <some date>. On that date, we'll ship what we have done." The scope of what gets shipped does not have to be set in stone the moment the deadline is created. Agile development is all about managing scope and communicating progress inside time-boxed increments, which are all actually mini-deadlines of their own.
    – Eric King
    Feb 26, 2016 at 0:45
15

Who is to blame?

Managers, legal dept, accountants - take your pick...

I know the example is somewhat contrived but the fact that the company could walk away without paying a dime if they weren't 100% satisfied should have rung immediate alarm bells as should mixing waterfall and agile thinking.

Customers want to have their cake and eat it - they're happy to accept waterfall, mini-waterfall, agile, la-la-land as long as they get product X for $Y by date Z.

Agile development absolutely requires the development team and customer to be on the same page from a methodology point of view. Thinking differences in culture will just come out in the wash is wishful thinking.

12

IT projects deal with unknowns; some of these unknowns are even unknown unknowns. What does that mean?

Take for example a toy bridge for your model railroad. There are all parameters known to you:

  • You know how big the valley is

  • You know the material of the mountains, their height, stability etc.

  • You know how much material you need

  • You know from earlier "projects" how long it took you to build similar things

There are many variables involved which influence your calculation of investing spare time and money. But you could say without a thought, whether it is finished next weekend.

Take the example a step further:

  • Say you do not build the bridge for your own model railroad, instead you build it for a complete stranger: your job is to build a railroad bridge between two mountains

  • Say you have near to no information in advance of the model landscape

  • The information about the landscape is, that is has two mountains, which seem not too big

  • The consistency of the mountain is between rock and jelly

  • Total cost has a max of 10$

  • The workplace is complete dark and there is no chance of light: you only have a box of 8 matches

  • The deadline is 3 hours

That would be the analogy to an IT project. You have experience in building bridges and it is easy to walk on known terrain. What it makes hard is the darkness. There are many things you can hardly predict: The measures of the mountains are only known after poking some time in the dark. So is the consistency of the mountains. From that you could make estimates on how long it will take you and how much it will cost. Here the unknowns are things, which you do not know on the beginning of the project like the concrete terrain etc. But there are things you can not foresee, even with the most experience and most conservative estimations. These things are the unknown unknowns which bear a bit of chaos.

Every IT company should know that. They have to deal with project risk.

1) There are several ways to minimize the (financial) risk: the deal could include tha the customer pays for every working increment. So after increment 1 is delivered, a partial rate has to be paid. As long as Scrum-Addicts LLC delivers, there is minimal financial risk. The more finegrained sprint goals are planned, the lower the total risk of every sprint. That means, if Money-Bags Corporation received 80% of the contract they should at least paid 80% of the contract value. If they refused to pay after a failed sprint the risk isn't as high as the refuse to pay 100%.

2) Scrum-Addicts LLC has a problem with their developers

Scrum-Addicts managers consult their scrum team, and the team says it will take 3 week-long sprints to complete all of the features Scrum-Addicts manager adds 1 week to be safe, promises to ship the software in 1 month and signs a contract with Money-Bags

That suggests, that a) the developers aren't experienced with scrum or b) they are doing scrum wrong The longer teams work with scrum, the better are their estimates. If the teams makes estimations and the manager adds a "buffer" as "safety", the manager seems to know better than the team, which is a bad sign. If you have an experienced team, there is no need for a "managerbuffer", the team included that already in the estimation. The idea is, the more sprints the team has worked together the more the team knows its strengths and weaknesses and has some metrics to make realistic estimates. Of course there are - as already mentioned - the unknown unknowns which tend to make estimates hard; or at least imprecise. But in the long run, the estimates should get better and better.

Who is to Blame?

1) Management

As said above: there is clearly a failure in risk management. If the company is on the brink of bankruptcy, the company deserves it. If you work at such a company: leave!

2) The Team

Even if management is utterly stupid, the team should have spoken up against such a project. A good manager should know the risks; but a good developer should point out risks. And most of all: The team should report early if something fails.

What Is to Be Done?

Now: Take Money-Bags to court

For the future: Do not make such contracts

Scrum is not to blame for management failure. Scrum was developed based on the experience of many IT projects failing. It can not prevent failure, nor can it cure incompetence of teams or management. The basic idea is:

  • to structure communication ways (who talks to whom when about what)

  • to encourage developer reporting failure early

  • to divide problems in tasks and subtasks

  • to structure time and capacities (who works when on what)

  • to distribute the tasks over the time slots

  • make the unpredictable a bit more predictable (planning poker)

or overall: to minimize risk.

Scrum is a tool as a hammer is. Whether it is a good tool depends on your knowledge how to use it. But sometimes a screwdriver fits better. It's up to you.

1
  • 1
    There's another aspect of Scrum that is vitally important to understanding why this project failed: scrum embraces failure. It is expected that the first couple of sprints of a new team or project will fail. Through the scrum process of retrospectives the team will improve itself and over the long term become accurate in their estimates but only as long as they remain the same team working on the same project. When either of those change you should once again expect some failure since the underlying variables are shifting.
    – Cronax
    Feb 26, 2016 at 11:24
9

First off, "Who is to blame?" is the wrong question to ask. Assigning blame is fun and all, and will probably make everyone except the blamed person(s) feel relieved (in a "hey, it's not my fault, the boss said so!" sense), but it's not a productive use of your time, and can actually be counterproductive and cause a drop in employee morale.

A better way to look at it is "What caused the delay?". Was it lack of experience in the technology? Critical bugs which were not detected in testing/QA? Lack of testing/QA? Too optimistic in the estimation? Not taking into account the team's not-so-optimistic estimations? Somebody got hit by a bus? Whatever the cause, the next question is "How do we make sure this doesn't happen again?". In some (hopefully rare) cases, the answer for that might be "get rid of so-and-so", but if you start from "I need to punish whoever's responsible", you're unlikely to see the majority of the cases where it is not the right solution.

Within the project, you're already sunk. Deadline's come and gone, you warned the customer as soon as was apparent it was going to slip (because you did do that, right? If not, that's part of the problem), and now it has to be handled however it was spelled out in the contract (it is actually spelled out in the contract, right?). Generally speaking, that should involve negotiating with the customer how you are going to deliver what is missing. Lots of people like to think of a contract as something that cannot be changed, but faced with either a) dropping the contract and not having what you bought, b) suing the company for breach of contract and spending a lot of money in court, and c) negotiating how to get their product with the least amount of trouble possible, most companies choose c.

Looking forward, before quoting a price/deadline to a customer you should analize the risks involved in a slipped deadline or cost overrun (what are possible causes for such a thing? Which causes can you mitigate somehow, and which you can't and just have to plan for), and use that information to help decide on what you are going to promise. If it is a case where it's 100% or nothing, you'll obviously quote higher prices and longer deadlines, because the risk is higher.

You'll notice I didn't talk about Agile in this whole answer. That's because (I'm going to forget about the customer's involvement in Scrum for a second, although it is very, very important) at this point it doesn't really matter. You'll be faced with this problem in Agile, Waterfall, or whatever development process you use. Yes, Agile is supposed to help you manage risks better, by letting you see if they've become actual problems earlier, and involving the customer in the process itself so they are always informed, but it's not a panacea.

4
  • 3
    -1 The point of agile is that many of the risks simply cannot be predicted. For example, they added 1 week buffer in case things slip up. You can always triple time needed, but then you loose against competition that doesn't do that. Agile should adopt "Its done when it is done" mentality. Which is simply incompatible with contracts and deadlines as described.
    – Euphoric
    Feb 25, 2016 at 9:20
  • 3
    @Euphoric I cannot entirely agree. Yes, the point of Agile is that many risks cannot be predicted, and that's what the buffer is for, I'll grant you that. However, that doesn't mean that all risks are unpredictable, nor does it mean that you should go into a project blind, without considering the risks that you can predict.
    – Iker
    Feb 25, 2016 at 10:20
  • 2
    @Iker The one does not preclude the other, but the point of being truly agile in the development process is that "It's done when it's done" mentality for both the customer and the team. Sure, there are always some risks you can predict, but you can never successfully predict all possible risks and exactly what impact they will have on your progress. Unless you can see the future somehow. That's why Agile work requires specific contracting, where you agree that "we'll continue working until the money runs out, or either party is no longer willing or able to, or all the customers needs are met"
    – Cronax
    Feb 26, 2016 at 11:19
  • ok, i upvoted this for the immediate rejection of blame as a concept. I agree that blame is an unproductive component that's a distraction from success. Let's change the question. Maybe we could make it "how could we have handled this"? "how can we turn this into a success for us?" "what changes from every party could have resulted in a positive outcome?" i might be ok with changing "blame" to "responsible", but as every project with a vendor and a customer is a team interaction, isn't the entire global scoped 'team' responsible anyway? the question of who is to blame then becomes rhetorical.
    – Joshua K
    Feb 29, 2016 at 23:06
4

Firstly, this is a problem with any development methodology. At least with an iterative development system you have something to show the customer at the end of the deadline, which may be enough to get an extension to complete the product (even if the customer doesn't pay any more!).

There are cases where a deadline is a deadline however, imagine you're writing a game and it absolutely has to be released in time for the Christmas holidays. Getting that wrong has bankrupted many a company!

For agile methods that have to complete a certain amount of features by a certain date, scrum is probably not the best method to use (as I've always found that scrum makes dev go slower and does not allow enough agility to alter the process when needed.

What you need, regardless of methodology, is to set up a backlog of required features to give visibility of progress. Progress on a per-sprint basis is not good enough, you will not know if you're meeting the ultimate target. So a kanban-style methodology would be better: set all the features on the left, and work them through the system to to show progress to completion.

That focusses people's minds on what still needs to be done in a way that Scrum doesn't handle, and allows people other than the dev team to see what remains and whether you're likely to meet the target (and thus manage customer's expectations early, or arrange those overtime bonuses before they're needed).

Scrum is a system that potters on forever, continually defining and refining something. Its simply not suitable for this kind of development. Others can manage this sytle and still keep the iterative development concept, Kanban is one like that, Crystal another. But what is essential to understand is that if you're following Scrum religiously, you're not being agile. Any true Agile system should be able to morph to cope with these particular issues, that's why it was called agile in the first place, its about getting done what needs to be done, and if a fixed deadline is part of that, then you should be factoring that into the way you work.

6
  • 6
    "Game ready for christmas" could be a posterchild for Scrum. Ship the 80% you have finished, sell the remainder as DLC. That's not the hypothetical situation discussed here, where the deadline fixed both time and scope, with a 100% penalty for partial delivery.
    – MSalters
    Feb 25, 2016 at 11:38
  • 2
    @MSalters you assume the game works at all, that 80% may not be missing features that can be added later, but breaking functionality or crashing bugs. It doesn't have to be a game, could be any software that needs to be shipped for a definite, and unchanging deadline (as not even Apple can postpone Christmas!)
    – gbjbaanb
    Feb 25, 2016 at 11:46
  • 6
    That's the basic premise of Scrum! Broken functionality doesn't count. If you come from a Waterfall background, you'll find that Scrum therefore prioritizes bugfixing over adding new features. "80% done" means that there are missing levels, missing bosses, etc.
    – MSalters
    Feb 25, 2016 at 11:52
  • 1
    @gbjbaanb By that reasoning, something could be 99.9% done but still not work because it crashes immediately upon startup.
    – user253751
    Feb 25, 2016 at 20:25
  • @immibis but that is true though. Things like games do not tends to leave features out until the end, most parts of a game have to be implemented for the whole to work - while you can take out some features (and I know games that have done this) they do not add features incrementally. So a missing boss would be a broken game. I only chose games as an example as they do tend (particularly before internet delivery) as examples of hard deadlines.
    – gbjbaanb
    Feb 26, 2016 at 8:35
4

The development paradigm is out of sync with the contract paradigm. Ideally, the way contracts are written would change, but that's unlikely to actually happen. However, even if you were to drop scrum, you would still have surprises and missed deadlines (only you'd likely be much later because you did all that design up front and it was all wrong!!).

With or without a change to how contracts are written, you ship what you've got working. Then fulfill the contract by eating a cycle of development time in order to finish the features you didn't get done.

Is it good that you failed to deliver everything you promised on the day you promised? No, but your customer will be much happier if you can deliver something that works on time, then deliver the rest of it quickly after than if you're simply running late and don't have anything at all to give them.

6
  • 3
    Yes, sometimes the customer is happier if the team delivers at least some portion working features, but this is not always the case. I'm talking about cases when (1) the product is useless to end-users unless 100% of features are implemented (for example, it requires expensive certification that needs to be done only when everything is finished) or (2) the customer is an old-school company with the "all-or-mothing" approach: if the product is not 100% ready we consider it failed, break the contract and fire everyone responsible. Feb 25, 2016 at 8:26
  • 2
    The customer will always be happier to see progress in the way of working software. The expensive certification can wait until the product is up to their satisfaction. Releasing it to the client doesn't mean they have to release it to the public. In case 2, there's really no option but to have your legal/sales teams write better contracts. Honestly though, your problems would be the same, if not worse, with waterfall there.
    – RubberDuck
    Feb 25, 2016 at 8:34
  • 2
    @AndreBorges Surely the customer will be happier to see 80% of features than to see 0% of features? At least that way, the customer knows the product is mostly done.
    – user253751
    Feb 25, 2016 at 20:22
  • @immibis, if you say that, it means you've been happy enough to avoid some 'peculiar' customers in your work. There exist some huge clumsy government-related corporations that enforce not-so-reasonable contract terms, but if you invest all your resources into their task and manage to succeed, they pay serious money that could lift your small company sky-high. However, if you fail, you may find yourself looking for a new job. It's the risk that that some people are willing to take. Feb 26, 2016 at 7:07
  • 2
    Exactly! Due to its internal bureaucracy and lack of experienced management staff, sometimes it's easier for a large company to consider a failed deadline an "unsuccessful experiment" and drop the project altogether, than to put further effort in trying to communicate and renegotiate the scope. Sad, but true :( Feb 26, 2016 at 7:33
1

Many Scrum books and articles say that a failed sprint (when the team fails to complete some features from the Sprint Backlog) is not something that bad, it happens from time to time, and it can actually be useful if the team learns from their mistakes and improves something in the following sprints. And the team should not be punished for not completing the work they committed to.

The way you "punish" this kind of behavior is by limiting the amount of work the ones who didn't finish can take on next sprint. Chances to work on cool stuff are vanishing. The reward for doing good work is more work.

This looks great from the developer's point of view, however, let's say we have a software company "Scrum-Addicts LLC" developing something for serious clients ("Money-Bags Corporation"):

Scrum-Addicts managers suggest making a piece of software for Money-Bags They agree on a list of features, and Money-Bags asks to provide a shipping date Scrum-Addicts managers consult their scrum team, and the team says it will take 3 week-long sprints to complete all of the features Scrum-Addicts manager adds 1 week to be safe, promises to ship the software in 1 month and signs a contract with Money-Bags After 4 sprints (shipping deadline) Scrum team can only deliver 80% of features (because of inexperience with the new system, the need to fix critical bugs in previous features in production environment, etc...) As Scrum suggests, at this point, the product is potentially shippable, but Money-Bags needs 100% of features, as mentioned in the contract. So they break the contract and pay nothing.

Scrum-Addicts is on the brink of bankruptcy because they got no money from Money-Bags, and the investors were disappointed with the results and are unwilling to help the company any more.

If on Monday I bet you $100 that it will rain on Thursday and it doesn't rain until Friday you'd be right to take my money. If, rather than a chance to gamble, what you want is a weather forecast then we need a contract that lets me give you an updated forecast on Tuesday.

Obviously, no software company wants to be in Scrum-Addicts' shoes. What I fail to understand about Agile and Scrum is how they suggest teams should deal with planning and deadlines to avoid the situation described above.

Think about WHY MB wants to take their ball and go home. MB didn't demand the work be done in a month at the outset. SA promised 100% of critical features in one month and didn't deliver. SA set the deadline not MB. SA even arbitrarily added a week to the deadline. So why is this a deadline?

Occasionally when competing for work software companies give in to the temptation to show off and promise the moon. Professionals carefully establish whether a moon is even required. Which is the more critical need for MoneyBags? 100% of features or a functioning product in a month's time? Do they even know what is truly critical? Is there some upcoming event setting a hard deadline?

If I was Scrum-Addicts negotiating this contract I'd want to know a lot more about Money-Bags business needs and structure the contract to grant as much flexibility as Money-Bags is comfortable with. I'd teach them how the agile process works so they know what to expect from us.

This way rather than expecting everything to be suddenly working perfectly in a month they'd be expecting to be evaluating the first deliverable in 1 to 2 weeks.

So, to summarize, I have 2 questions:

Who is to Blame? Managers, because it's their job to do the proper planning
The team, because they committed to doing more work than they could
Someone else

Anyone could have stopped this travesty before we got a month down the road.

I could go as far as blaming Money-Bags Corp for hiring a team that obviously fraudulently represented a waterfall process as being agile. The contract itself makes it clear this is not agile. Planning to be done in a month doesn't make it agile.

If you insist that it's agile, it's agile with only one sprint that is a month long. Which, yeah, I wouldn't recommend because that's, again, the same thing as waterfall.

What Is to Be Done?

How about agile? Deliver something every sprint? Get feedback before the deadline? Week long sprints? How about renegotiating the draconian contract the very moment you suspect the deadline is in danger rather than hiding and praying? At the very least you can stop wasting time on a doomed project and find a more reasonable customer.

The managers should move the deadline 2x (or 3x) times later than the original team's estimate.

Deadline multipliers are about as useful as setting your watch 15 minutes early so you'll never be late. You can only fool yourself so long before you realize what you're up to.

Early estimates are wrong. Try to capture how wrong. 5 weeks, give or take a few weeks is a simple expression that lets you express how uncertain the completion date really is. Rather than trying to guess accurately, you guess how wild your guess is. Do some real work and get some real data. Then you can start making estimates with a narrower range. One to two weeks is plenty of time to do this.

Team members should be encouraged to do all the work they committed to no matter what (by issuing penalties for failed sprints)

Team members should be encouraged. Failed, committed, or otherwise. Rather than constructing any artificial consequence such as punishments or even bonuses (carrot and stick) studies have shown that people doing creative work such as programming respond best if provided three things: Autonomy, Mastery, and Purpose.

Daniel Pink has a TED talk about this. The talk is about motivation not agile but I easily saw how to map these points to agile:

Autonomy - I want to direct my own life - Let me pick work from the backlog.
Mastery - I want to get better at something that matters - Customer feedback.
Purpose - I want to be part of something larger than myself - A collaborative team.

The team should drop Scrum because it doesn't fit the company deadline policy Scrum can hit a deadline more accurately than waterfall. Given a deadline scrum can meet it. It might meet it with only 1 of 47 features depending on time, feature, and skill but it can meet it.

An agile project can be styled so extremely that every night when the team goes home it's ready to ship. This seems silly unless you think of shipping as asking the customer to test and provide feedback. The sooner that happens the sooner you can make adjustments. This hits every possible deadline. Just not every feature. But it steers you to the features that matter.

We should all drop software development and join a monastery

Right, like locking me up in a room away from real life is gonna make me write LESS code.

I've edited this answer down to size. If you're curious read the edit history.

4
  • I'd like to just assume you meant sprint not backlog - I meant exacly what I wrote in the question: the sprint backlog Feb 29, 2016 at 6:38
  • people doing creative work such as programming respond best if provided three things: Autonomy, Mastery, and Purpose - this can be a huge topic for speculation on its own, but the fact is that unfortunately a lot of programming work is becoming less creative and more routine (dull tasks, fixed tech stack and feture sets, strict contracts). Hence, in many cases carrot and stick works just fine. Feb 29, 2016 at 7:46
  • @AndreBorges You're right, I was thinking of the product backlog. Recently I've been working with a tool that calls the sprint backlog the sprint and the product backlog the backlog. You caught me losing the fight to keep my vocabulary from becoming proprietary. Feb 29, 2016 at 9:23
  • @AndreBorges programming will never be envelope stuffing. It is firmly a candle problem. The reason why is because any repetitive problem can be solved with the same code that solved the first problem. Despite this management can get into a mindset where they think creativity is a problem to be stamped out. I've worked for and ran from several of these shops. They don't keep good people. They don't produce good software. Developers are craftsmen. Trying to turn them into assembly line workers only hurts your cause. My job is not to flip eggs. It's to ensure that eggs are flipped. Feb 29, 2016 at 9:45
0

Everyone has to be agile. Whatever you decide that will be, look like, who does what, how, when, where and why by all parties. Agile customers, management and developers.

You cannot give a shipping date too far into the future. You give an estimate.

Someone needed to manage the client's expectations. The reason you don't worry too much about having a couple of sprints fall behind is because you adjust to prevent the entire project from falling behind. If you come to the conclusion after a sprint or two that you're not going to finish meet the "shipping date", that's when you tell the client.

Now what do you want to do? Get rid of features you don't need or move the date. If you could deliver on time, you would. Don't hesitate to bring bad news.

Who knows, on some projects, you may ship sooner.

You can't be agile if the client doesn't want to.

0

Goal

I believe the following two "metrics" should be the basis for any business decision:

  • is the work profitable (for the client)
  • are we working as efficient as possible

These are quite universal. Of course it get's more complicated very fast, for example, work being profitable is about the product doing the right thing, the user being able to use the product, the product being marketed correctly etc. - for a lot of these "Scrum-Addicts LLC" is not bearing responsibility.

Issue

The contract is not focusing on the goals outlined above. There's an "all or nothing" clause - get everything done and be paid, or get nothing done and don't be paid. However, this does not directly relate to value being created. Another downside which follows: now we need to spend time & money assure and verify that the contract is being followed. Why on earth would we want to spend this money? How does making sure a contract is fulfilled help when the requirements have changed in the meantime and we've found out that the ordered piece of software is not creating any value? There's just more money going down the drain! Now, of course, there's a reason for this behavior:

  • Culturally we are used to shop for things like that. We expect shop for software as we would for a car: pick a configuration, be given a price and deadline, and be very unhappy if those two aren't met.
  • we want to offload risk and accountability
  • we want stability, it helps with planning and makes us feel better (and also our client, which is an important aspect!)

At the end of the day, we'll have to choose a compromise which will allow us to satisfy our goals as good as possible.

This is how it should work

  • have a contract for services & work instead of for a product
    • needs to be terminable on relatively short notice
  • work closely together to ensure optimal efficiency
  • involve all the necessary parties, both from "Scrum-Addits LLC" and "Money-Bags Corporation" - a "single point of contact" tunneling all the information is not going to work here

well i basically just said "be agile". Now here's why:

  • process & contract are optimized to spend as much money on the Goal as possible
  • you'll have to trust the contractor to do his job, and not need to invest a lot of money verifying that he's up to the job.
  • the ability of suing your contractor if your expectations / contract isn't met usually doesn't help, because doing so will cost more than just dropping it. Some of the main concerns here are time-to-market. You most likely will lose way more money/business by going to court than you'll get.
    • at the end of the day you'll just have to bear some risks yourself.