I need some help in answering questions
This is Sprint 1 and I have a 2 week sprint with the first week completed and the current burndown chart looks like:
Day 1 with 50 Story points
Day 2 with 57 Story points
Day 3 with 50 Story points
Day 4 with 34 Story points
Day 5 with 25 Story points
It is assumed that work is only done on working days, so 10 days in a sprint. The remaining 5 days have not been completed.
1) What is the expected velocity for this sprint?
According to a search on google, a sprint's velocity is the amount of story points in a sprint e.g. 50 story points in total in a sprint = sprint velocity is 50.
2) What do you think the velocity should be for the next sprint?
Again from a search on google, if sprint 1 has 50 as its velocity and Sprint 2 has 40 user stories in total, therefore the velocity is 40. So (50 + 40)/2 is 45 velocity?