Questions tagged [sprint]

A sprints in Scrum, or otherwise known as an iteration, is the heartbeat of the Scrum cycle.

Filter by
Sorted by
Tagged with
3
votes
2answers
217 views

Team focusing on tasks, but not on User Stories

We have an architecturally layered application, with web frontend, java backend, java and python microservices, DB etc. so when we do a User Story representing business value, it's mostly broken down ...
1
vote
3answers
147 views

As a developer, how should I work differently in kanban vs scrum?

I am a junior back-end developer at a large company in the US. At the moment, my 10-member team is changing its approach from Kanban to scrum (2 week sprints). My current way of working is this: I ...
6
votes
2answers
395 views

How to avoid code review bottlenecks when some of the team pair program

There is a school of thought that describes code reviews as the number one priority activity for all developers in a sprint since they are either: a) A source of unrealised value b) A source of bugs ...
-1
votes
1answer
83 views

How much front-end design must be done before every Sprint in Scrum?

I'm a front-end developer working as a member of an agile team. I have no clue how much of UI/UX must be done before every sprint and how much of it I can postpone for later.
1
vote
2answers
83 views

Managing sprints for multiple releases of the same product for the same team

How do you plan a sprint for the same product with two releases when the same team will be working on both releases during the sprint cycle? To give some background, our product gets released out to ...
2
votes
1answer
246 views

Parallel sprints in Scrum - one project, two teams

Currently, I am working on the project that consists of two teams which we track also in the JIRA software tool and it is basically two teams that are working on the same project so this is my ...
0
votes
2answers
130 views

Planning a sprint when you don't know the next tasks

How should sprint tasks be planned when you won't know the next task to be done until the current task is complete? For instance, consider the case of optimizing a program's performance. Until you fix ...
0
votes
6answers
309 views

Not planned work emerges during the sprint from management?

I believe that most of us have encountered this situation. What is the best approach when higher management or client is forcing the PO to include some new functionality in the middle of the sprint, ...
3
votes
3answers
541 views

In scrum, if tasks are estimated in hours, how to avoid assigning the task in sprint planning?

I've been reading up a lot on the subject, and from what I can gather the following statements 'should' be true in scrum: 1) Estimate user stories in story points at the product backlog level. This ...
5
votes
4answers
358 views

Need help for sprint planning when tasks are not done in previous sprint

In our team we don't have dedicated Scrum Master, so one of the developer is playing the role of SM. I know this is wrong but it can't be changed. In our system, we assign story points to all the ...
0
votes
1answer
73 views

Agile process, assigning estimated tasks to people in a Sprint

Today I was surprised to hear that our Scrum Master and Product Owner decided that they wanted us to consider a change to how Sprint Planning was done. The change essentially is that all of the ...
0
votes
5answers
201 views

Does the Scrum Guide Specify How Often to Release QA/Test Builds?

See https://www.scrumguides.org/scrum-guide.html I've read through this several times and can't find anything about how often to do QA/Test builds during a sprint. There is a section called increment....
1
vote
3answers
204 views

Agile scrum - estimate another team's sprint

I heard a case where two teams are planning each others' sprints (estmating stories and deciding what goes into the sprint). The stated benefit is to solve one of the two team's problem with not ...
2
votes
2answers
121 views

Whom does the Nexus Sprint Backlog belong to?

The Nexus Guide states that: A Nexus Sprint Backlog is the composite of Product Backlog items from the Sprint Backlogs of the individual Scrum Teams. However, trying to build an analogy between ...
2
votes
2answers
107 views

Sprint planning: who decides which items of the Product backlog to be included into the Sprint backlog?

I am confused about the two following statements and how do they both influence on which items be included into the Sprint backlog: The Sprint Goal and Sprint plan is produced by the collaborative ...
0
votes
1answer
113 views

“Materialised” view of the Sprint Goal and consequences of its absence

The Scrum guide defines the Sprint Goal as: an objective that will be met within the Sprint through the implementation of the Product Backlog, and it provides guidance to the Development Team ...
2
votes
4answers
1k views

dev and qa in same sprint

I am not the first one to ask this but i also did not get anything concrete from other such posts to tell me what is needed so i am posing the question here. Feel free to refer to some other resource. ...
0
votes
6answers
632 views

Should agile sprints/iterations be back-to-back?

I know -- it depends, right? What I'm asking is whether the notion that sprints/iterations in agile development should always be back-to-back, with only a review and planning meeting to separate them ...
14
votes
5answers
2k views

How to deal with sprint planning running far too long?

I took over 5 hours in sprint planning for a week long sprint. That seems like too much. We discuss things in detail in sprint planning, as most of team members are not senior. If we don't it will ...
5
votes
2answers
284 views

Product Backlog vs. huge features

I am designing and documenting a product with agile process. When I write user stories to add them to the product backlog, I found myself in a complex and huge features. Should I write these features ...
1
vote
3answers
159 views

How to manage backlog preparation during current sprint

In my team, the Business Analysis is also a scrum team member. He will prepare all user stories to the Product backlog, but his tasks also should be managed with timeline/estimation. Should we put ...
2
votes
2answers
229 views

How Sprint works [closed]

I am not from a IT background. An idea is generated is being worked upon now. Initially we started with Waterfall methodology and now using agile. Want to understand how exactly this agile methodology ...
2
votes
2answers
244 views

Interrupting software development methodology

I'm in trouble, my team (3 devs including myself) works with mobile and backend development and we are dealing with some problems trying to order this process. Let me try to explain my situation, our ...
2
votes
1answer
361 views

What time of day should we end a sprint before a sprint review meeting?

Summary Our company runs two week sprints for our software development team. We have many projects our team shares with some being individual projects. We've noticed that when we end our sprint an ...
3
votes
3answers
1k views

Version number between sprints

My question is a little bit about branching, versioning and agile development in general, but the heart of all three is the version number I think. Currently, I'm using internal version numbers (e.g. ...
4
votes
1answer
1k views

Should there be a gap between sprints?

I've set our sprints up to last for 2 weeks, nominally 10 days. Day 1 starts with planning and then moves to start development. Day 10 has S&T and Retro, but also cleans up the release/tidies ...
2
votes
2answers
294 views

How should both a Scrum team project and individual Kanban projects be handled within JIRA?

Summary We're a medium sized company that has a development team of five team members. We recently started learning/employing the Scrum method to our R&D department. Our core team has one ...
1
vote
3answers
417 views

Is the Iteration Planning part of the Iteration itself?

If I split up the development into a timebox with 3 phases: planning (e.g. with planning meeting), functional progress (software development / implementing user stories) and finalization (e.g. with ...
8
votes
4answers
968 views

Do “almost finished” tasks or stories justify planning with overload in the next sprint?

The case in question: The sprint is almost over and one of my Scrum teams did not finish some tasks. (The reason for this is not essential for this question and will be addressed accordingly.) One of ...
1
vote
6answers
2k views

Is it appropriate to have a “clean up” sprint to start fresh without carry-over story points?

Our Scrum team has been having incomplete (not accepted) stories at the end of a sprint (usually 3 week sprint durations) that carry over into the next sprint. This has happened in every sprint except ...
3
votes
3answers
421 views

How to get started with Scrum when the team is bad at generating ideas?

I have a bit of a problem regarding implementing Scrum into a project. The team I'm working with is generally just very bad at coming up with ideas. I'm not sure if it's a matter of them not feeling ...
1
vote
3answers
217 views

Scrum Sprint Stories in Testing

I am a Scrum Master and have been practicing Scrum in my Organisation. We have now moved on to ServiceNow for development and we are facing issues now. Issue: We work on sprint->story->task, but, we ...
1
vote
3answers
264 views

How do I explain to my team “there is no problem if the requirements need to change after a sprint?”

My team is very inexperienced in how manager our only work and how much time is necessary to spend in some tasks. So many sample things like just develop what our client needs and show it for her (...
1
vote
1answer
671 views

How long does PI planning session in agile methodology actually plan for?

Does PI planning actually plan for only a few sprints ahead or does it plan for the whole project(all sprints until production)?
0
votes
2answers
257 views

Scrum - Calculating Sprint Velocity

I need some help in answering questions This is Sprint 1 and I have a 2 week sprint with the first week completed and the current burndown chart looks like: Day 1 with 50 Story points Day 2 with ...
3
votes
2answers
481 views

How the time of Agile Sprint is calculated?

have a query in my mind that how the time estimation is made in sprint meeting for agile work flow? Lets say for example: In a team there are 4 developers and the first sprint is designed for about ...
9
votes
8answers
606 views

Are bargaining and beat down attempts on Scrum estimations legitimate parts of the process?

I noticed in scrum meetings, that developers often give realistic estimations on stories. However, even rather simple stories need a lot efforts for configuration, setting up third party components, ...
4
votes
3answers
451 views

How to record changes to tasks in sprint backlog?

We are using Scrum for more than a year now for a mobile game project. We use a printed Excel sheet pinned on cork board almost similar to one here on mountaingoatsoftware website. During the sprint ...
33
votes
4answers
5k views

Scrum - What are team members busy with during a sprint

So, a scrum sprint is a fixed time period during which a specific set of features should be implemented. And a scrum team consists of all the people committed to delivering those features, the ...
81
votes
10answers
16k views

Dealing with failed sprints and deadlines

Many Scrum books and articles say that a failed sprint (when the team fails to complete some features from the Sprint Backlog) is not something that bad, it happens from time to time, and it can ...
1
vote
3answers
1k views

What happens if Sprint Goal is not met?

I've been reading Scrum Guide and one part is missing for me. What happens if Sprint Goal is not met at all? Let's say the Sprint Goal is a big part of a functionality which cannot be broken into ...
6
votes
3answers
347 views

How to deal with outlier programmers during sprint planning?

It is generally accepted that the best programmers produce at least an order of magnitude more than average ones. This seems like it would cause problems with the usual approaches to sprint planning ...
14
votes
6answers
1k views

How to handle 50% of worse than average sprints?

If I understand Scrum correctly, this is how I determine the work my team can take on in the next sprint: I average the number of completed points for the past several sprints. This quantity is our ...
3
votes
2answers
326 views

How does the result of Product Backlog revision during Sprint Review influence the next Sprint's Backlog?

On scrumguides.org, the following is said about the result of a Sprint Review: The result of the Sprint Review is a revised Product Backlog that defines the probable Product Backlog items for the ...
7
votes
5answers
1k views

In Agile SCRUM, how do you handle even distribution of work in a sprint between “experts”?

Where I work, we have a lot of silos of knowledge. Basically each member of the development team is the expert (and sometimes the only one that knows a thing) on certain pieces of the overall software....
2
votes
2answers
714 views

Handling the end of sprint cycle between testers and developers [duplicate]

I've convinced our organization to move to a full-team definition of "Done", i.e. one that includes the QA testing and not just code completion. As a result, we can now more accurately tell where the ...
1
vote
2answers
168 views

Integrating QA within agile sprints [duplicate]

I've been working in "Agile" for a while and am working to move more towards agile at a new company. One of the problems I have always sort of encountered is effective integration of QA within the ...
0
votes
2answers
142 views

Best way to offer team member help? [duplicate]

I've been having a problem recently. In my recent sprints, I have found myself finishing my work well before the sprint ends (several hours in a 2 week sprint). I am left with a lot of time and ...
1
vote
2answers
505 views

Agile. User stories, Tasks and Reporting

At the moment we are creating tasks based on (pointed) user stories. We then link the tasks to the user story in TFS and move them across the kanban board. Does this sound like a common approach? also ...
0
votes
3answers
496 views

Big tasks vs short list of small ones at sprint planning meeting

Simply: Sprint planning, we do not have well described user stories and we need to create tasks (since we do PoC-like module, technology remain somewhat unknown). Should a team either: Create big ...