Timeline for Is the following diagrams correct for RAD and Agile methodologies?
Current License: CC BY-SA 3.0
3 events
when toggle format | what | by | license | comment | |
---|---|---|---|---|---|
Apr 1, 2013 at 0:00 | comment | added | Thomas Owens♦ | @user1394925 I looked in two books and Wikipedia and they all use "cutover" (not "implementation") and "construction". But your source seems reasonable as well - I'm not sure if there's a particular standard. As long as you're careful and define the terms, I don't think there would be a problem. | |
Mar 31, 2013 at 20:28 | comment | added | user1394925 | Hi, Thanks for the details. I got the RAD steps from this study on page 7 casemaker.com/download/products/totem/rad_wp.pdf. +1. Is using implementation definitely incorrect or is it just preference to use cutover? | |
Mar 31, 2013 at 20:02 | history | answered | Thomas Owens♦ | CC BY-SA 3.0 |